Whole House Renovation Cost Calculator 2026 — Remodel Estimate

Estimate a whole house remodel by square footage, scope and finish level. Uses 2026 national per-square-foot data, with regional adjustments, phasing and contingency built in.

Whole House Remodel Cost Calculator

500–5,000 sq ft

Estimated Total Cost

$189,000

National average — actual costs vary significantly by location

Cost per sq ft

$105

Estimated range$108,000 – $270,000

* Whole-house remodel costs depend heavily on structural work, permit requirements, and regional labor rates. Add 20% contingency minimum.

How to Use This Whole House Remodel Calculator

  1. Enter your home's total finished square footage
  2. Choose the remodel scope: cosmetic, partial or full gut
  3. Pick a finish level: budget, mid-range or premium
  4. Read the estimate, then apply your regional factor and contingency from the tables below

The calculator returns a national figure. It is a starting point for budgeting and for judging contractor bids, not a quote.

Average Whole House Remodel Costs in 2026

Angi's national data puts a typical house renovation between $19,500 and $88,400, with an average of $52,275 for a 1,250–1,600 sq ft home. That average covers a broad mix of projects, from repainting and new floors to kitchen-and-bath renovations, so treat it as a sense of the middle, not a target.

Per square foot, the useful bands are:

ScopeWhat it usually includesPer sq ft
CosmeticPaint, flooring, lighting, fixtures, hardware, minor repairs$15 – $60
Partial / mid-rangeKitchen and bathrooms, some windows, targeted systems work$60 – $150
Full gutDown to studs, new plumbing, electrical and HVAC, new layout$150 – $300

Cost by Home Size

National figures at the low, middle and high end, based on the same Angi data:

Home sizeLow-endMid-rangeHigh-end
1,200 sq ft$18,000$72,000$180,000
1,500 sq ft$22,500$90,000$225,000
2,000 sq ft$30,000$120,000$300,000
2,500 sq ft$37,500$150,000$375,000
3,000 sq ft$45,000$180,000$450,000

Source: This Old House home renovation cost guide, updated 31 March 2026, citing Angi data.

Square footage is only the first input. A 2,000 sq ft house with one bathroom and a 2,000 sq ft house with three and a half bathrooms are different projects. Kitchens and bathrooms concentrate plumbing, electrical, tile and cabinetry into small rooms, and they carry most of the budget in any mid-range remodel.

Why Two Similar Houses Get Very Different Quotes

Age of the house. In a home built before about 1980, opening walls often means bringing wiring and plumbing up to current code, even if you only planned to replace finishes. That can move a job from the partial band into the gut band.

Systems replaced versus systems kept. Keeping the existing electrical panel, plumbing runs and HVAC equipment is the largest single difference between a $60 and a $150 per square foot project.

Layout changes. Moving a kitchen, adding a bathroom, or removing a load-bearing wall adds engineering, permits, new drain and supply runs, and inspections.

Finish level. The same scope with stock cabinets and laminate counters costs far less than with custom cabinetry and stone. The calculator's finish setting multiplies the base rate to reflect this.

Local labour. Labour is the largest share of most remodels, and it varies far more by region than materials do.

Regional Cost Adjustment

Apply a rough factor to the national estimate from the calculator:

MarketTypical factor
San Francisco Bay Area1.50 – 1.65×
New York City metro1.45 – 1.60×
Seattle, Boston1.35 – 1.50×
Los Angeles / Orange County1.25 – 1.40×
Denver / Boulder1.15 – 1.30×
Chicago, Minneapolis1.10 – 1.20×
Atlanta, Dallas, Houston, Charlotte1.00 – 1.10×
Rural Midwest and rural South0.70 – 0.85×

These are planning factors, not quotes. For more detail by metro, see the renovation cost by region guide.

Worked Example

A 1,800 sq ft house built in 1978 in suburban Denver. The owners want a new kitchen, both bathrooms redone, new flooring throughout, and the original electrical panel replaced.

StepFigure
Scope: partial, mid-range finishes$60 – $150 per sq ft
National estimate, 1,800 sq ft$108,000 – $270,000
Realistic point for this scopeabout $150,000
Denver factor, 1.20×about $180,000
Contingency for a 1970s house, 25%about $45,000
Budget to plan aroundabout $225,000

The panel replacement pushes this project toward the upper part of the partial band. Keeping the existing kitchen layout would bring it back down.

Budget Allocation: Where the Money Goes

For a mid-range whole house remodel, spending typically concentrates like this:

AreaTypical share of budget
Kitchen25 – 35%
Bathrooms15 – 25%
Mechanical systems (electrical, plumbing, HVAC)15 – 25%
Flooring, paint, trim, doors10 – 20%
Windows, exterior, roofing10 – 20%
Permits, design, dumpsters, cleanup5 – 10%

If your plan skips a category, move its share to contingency rather than spending it elsewhere. For costs of individual rooms, use the kitchen remodel calculator and the bathroom renovation calculator.

Phasing: Doing It in Stages

Many owners phase a whole house remodel over two or three years to spread the cost. Phasing works when the order is right:

  1. Envelope and safety first. Roof, drainage, foundation, electrical panel and any failing plumbing.
  2. Rough-in work next. Anything that opens walls: rewiring, replumbing, HVAC ductwork, insulation.
  3. Kitchen and bathrooms. Expensive rooms that depend on the rough-in being done.
  4. Finishes last. Flooring, paint and trim, once no other trade needs to cut into them.

Doing finishes first and systems later is the most common and most expensive phasing mistake. New drywall and flooring get torn out when the electrician or plumber arrives.

Timeline

ScopeTypical duration
Cosmetic2 – 4 months
Partial / mid-range4 – 8 months
Full gut8 – 18 months

Add four to eight weeks before work starts for design, bids and permits. On a gut remodel, permit review alone can take longer than that in large cities.

Costs Most Estimates Leave Out

  • Temporary housing. Required for most gut remodels and many mid-range projects. Two months of rent can equal the entire contingency.
  • Storage. A storage unit or portable container for the contents of the house.
  • Hazardous materials. Testing and abatement for asbestos or lead paint in older homes, which must happen before demolition.
  • Code upgrades. Once walls are open, inspectors may require smoke detectors, GFCI and AFCI protection, egress windows or other upgrades.
  • Utility increases. A larger electrical service or new gas line can involve the utility company and its own fees and schedule.

How to Use the Estimate With Contractors

Write a scope document before you ask for bids: which rooms, which systems, what finish level, and what stays. Send the same scope to at least three contractors. Bids on a written scope can be compared line by line; bids on a verbal description cannot.

If a bid comes in far below the calculator's range for your scope, ask what it leaves out. The usual gaps are permits, electrical and plumbing upgrades, and allowances for fixtures and finishes that are set unrealistically low.

Frequently Asked Questions

How much does a whole house remodel cost in 2026?

Angi's national data puts a typical house renovation between about $19,500 and $88,400, averaging $52,275 for a 1,250-1,600 sq ft home. Per square foot, that works out to roughly $15-$60 for cosmetic updates, $60-$150 for a mid-range renovation, and $150 or more for a gut remodel that replaces systems. For a 2,000 sq ft home, that is about $30,000, $120,000 and $300,000 at the low, middle and high end.

How much does it cost to remodel a 1,500 sq ft house?

Roughly $22,500-$90,000 for cosmetic work, $90,000-$225,000 for a mid-range renovation, and $225,000 or more for a full gut remodel. Where your number lands inside those bands depends mostly on how many kitchens and bathrooms are included and whether plumbing, electrical or HVAC is being replaced.

Is it cheaper to remodel or build new?

Usually cheaper to remodel. A cosmetic or mid-range renovation costs a fraction of new construction. The comparison only tightens on a full gut, where you pay for demolition and for working around existing structure. If a house needs foundation repair, a new roof and complete rewiring at the same time, get a new-build quote alongside the remodel bids.

How long does a whole house remodel take?

Cosmetic work takes two to four months. A mid-range renovation that includes the kitchen, bathrooms and some systems takes four to eight months. A full gut typically runs eight to eighteen months once design, permits and inspections are counted.

How much contingency should I add?

Twenty percent for most whole house projects, and closer to 25-30% for homes built before about 1980, where demolition is more likely to uncover outdated wiring, galvanized plumbing, asbestos-containing materials or structural repairs.

Can I live in the house during a whole house remodel?

During cosmetic work, usually yes. During a mid-range renovation, only if the work is phased so one bathroom and a basic kitchen stay usable. During a gut remodel, almost never: budget for two to twelve months of temporary housing, which many homeowners leave out of the estimate entirely.

What should I prioritize in a whole house remodel?

Anything that keeps water out and the house safe comes first: roof, foundation, drainage, electrical and plumbing. Then the rooms that are expensive to redo later, the kitchen and bathrooms. Paint, flooring and trim come last, because earlier trades would damage them.