What Renovation Permits Cost and Which Projects Need One
Which renovations need a permit under the IRC, and what permits cost: Fixr puts a kitchen remodel permit at $150–$900. Real 2026 city fee schedules compared.
Two questions come before a renovation budget is final: does the job need a permit, and what will it cost? Both answers are local. Most US towns adopt the International Residential Code (IRC), then amend it and publish their own fee schedule.
This guide answers both by project type. National ranges come from the cost guides behind our calculators. Local examples come from four real fee schedules (Dublin, California; Maplewood, Minnesota; Sammamish, Washington; New York City) and show how far fees spread. None of them is a national price.
Short answer: Under the IRC you need a permit to build, enlarge, alter, repair, move or demolish a house, and almost any change to its electrical, gas, mechanical or plumbing systems. Painting, papering, tiling, carpeting, cabinets and countertops are exempt. Fixr puts a kitchen remodel permit at $150–$900 and a bathroom permit at $150–$1,000. Your building department's fee schedule is the only exact answer.
What the Code Says: the Permit Rule and Its Exceptions
IRC section R105.1 is the starting point: before you construct, enlarge, alter, repair, move or demolish a building, or change its occupancy, you get a permit. Section R105.2 then lists the work that is exempt. Everything not on that list needs a permit unless your town has amended it.
Federal Way, Washington publishes the R105.2 list on its permit page. In short:
| Trade | Work exempt from a permit under IRC R105.2 |
|---|---|
| Building | Painting, papering, tiling, carpeting, cabinets, countertops and similar finish work; one-story detached accessory buildings up to 200 sq ft; fences up to 6 ft; retaining walls up to 4 ft that don't hold back a surcharge; sidewalks and driveways; decks up to 200 sq ft, no more than 30 in above grade at any point, not attached to the house and not serving the required exit door |
| Electrical | Minor repairs such as replacing lamps; reinstalling receptacles (not adding outlets); replacing a breaker of the required capacity in the same location; wiring under 25 volts |
| Gas | Portable heating, cooking or clothes-drying appliances; replacing a minor part that doesn't change the equipment's approval |
| Mechanical | Portable heaters, ventilation and cooling units and evaporative coolers; replacing a minor part that doesn't change the equipment's approval |
| Plumbing | Stopping leaks, unless a concealed pipe or trap is replaced; clearing stoppages; removing and reinstalling a toilet without replacing or moving valves, pipes or fixtures |
Ordinary repairs are exempt as well, but the IRC's repair clause (R105.2.2) does not cover cutting structural members or changing required egress. Exempt work still has to meet the code: Clark County, Washington reminds owners that permit-free projects must still meet setbacks and height limits.
Local amendments move the edges. Federal Way exempts fences up to 6 ft; Clark County exempts fences up to 7 ft. Clark County requires a permit for every re-roof and for replacing any window or siding, and in Washington electrical permits there come from the state Department of Labor & Industries, not the county. New York City's Department of Buildings lists painting, plastering, installing new cabinets, replacing plumbing fixtures, resurfacing floors and non-structural roof repair among work that doesn't need a DOB permit (some items carry conditions).
How Permit Fees Are Calculated
Building departments use four methods, often more than one on the same project.
1. Flat fee by job. The schedule lists a price per job type. Dublin, California's residential schedule (fees effective July 1, 2026) charges $880 for a kitchen remodel without structural changes, $600 per bathroom remodel and $326 for a single-family roof replacement.
2. Valuation table. You declare the value of the work, and the fee steps up with it. Maplewood, Minnesota's 2026 table charges $460.01 for the first $25,000 plus $11.97 for each additional $1,000 up to $50,000. Sammamish, Washington's 2026 table charges $710.28 for the first $25,000 plus $11.37 for each additional $1,000 in the same bracket.
3. Minimum plus a rate per $1,000. New York City charges a $130 or $170 minimum for the first $5,000 of an alteration to a one- to three-family house, plus $2.60 per additional $1,000.
4. Per square foot. Fixr puts per-square-foot permit pricing at $0.15–$0.85 in general.
Add-ons raise the headline fee:
- Plan review. Maplewood and Sammamish both charge 65% of the building permit fee when plans are reviewed. Maplewood's mechanical plan review is 25% of the mechanical permit fee.
- Trade permits. Electrical, plumbing and mechanical work is often permitted and priced separately from the building permit.
- Surcharges. Sammamish adds a 15% technology fee to its permit fees and a $91 energy code fee on residential remodels and additions. Maplewood adds a $1 state surcharge to fixed-fee permits.
- Re-inspections. Maplewood charges $100 an hour, Sammamish $180 an hour and Dublin $248 per re-inspection when work isn't ready or fails.
National Permit Ranges by Project
These ranges come from the national cost guides behind our calculators and describe typical fees across many jurisdictions.
| Project | Typical permit cost | Source |
|---|---|---|
| Kitchen remodel | $150–$900 | Fixr, building permit guide |
| Bathroom remodel | $150–$1,000 | Fixr, building permit guide |
| Basement | $200–$1,500 | Fixr, building permit guide |
| Deck | $100–$500 | Fixr, deck cost guide |
| Roof replacement | $100–$500 | Fixr, roof replacement guide |
| Window replacement | $50–$300 | Fixr, window replacement guide |
| Electrical, simple work to major rewiring | $75–$900 | This Old House |
| HVAC replacement | $250–$750 | Today's Homeowner |
| Whole-house repipe | $100–$400 | Plumbing Price Guide |
| Garage conversion | $300–$1,500 | Fixr, building permit guide |
| Home addition | $400–$1,850 | Bob Vila |
| Whole-house renovation | $500–$2,500 | This Old House, citing Angi |
The Same Jobs in Four Fee Schedules
Here is what four real fee schedules charge today. These are four places, not a national average. Valuation-based rows show the building permit plus plan review; trade permits are extra where the schedule lists them.
| Job | Dublin, CA (eff. July 1, 2026) | Maplewood, MN (2026) | Sammamish, WA (2026) | New York City |
|---|---|---|---|---|
| $15,000 bathroom remodel | $600 per bathroom | about $488 | about $832 + 15% tech fee | $156–$196 filing fee |
| $30,000 kitchen remodel | $880 (no structural changes) | about $858 | about $1,266 + 15% tech fee | $195–$235 filing fee |
| $100,000 addition | not a flat fee | about $1,942 | about $2,109 + 15% tech fee | $377–$417 filing fee |
| Roof replacement | $326 | $145 | $269 | not listed |
| Furnace or AC | $262 per unit | $120 furnace, $40 AC | $134 furnace or heat pump | not listed |
| Water heater | $157 (gas) | not listed | $134 | not listed |
| Window replacement | $367 for the first 5, $13 each after | $145 | not listed | not listed |
| Electrical panel | $219 | $125 | valuation-based | not listed |
How the valuation rows work out: in Maplewood a $30,000 kitchen is $460.01 + 5 × $11.97 = $519.86, plus 65% plan review ($337.91). In Sammamish the same job is $710.28 + 5 × $11.37 = $767.13, plus $498.63 plan review, before the technology fee and the $91 energy code fee.
Permit Rules and Costs by Project Type
Kitchen remodel
New cabinets, countertops, backsplash tile and paint are finish work, exempt under R105.2; NYC's DOB also lists installing new cabinets as permit-free. The permit line is crossed when the job moves the sink or dishwasher (plumbing), adds circuits (electrical), moves a gas range (gas), or removes or opens a wall (building). Each time the reason is the same: the inspector needs to see pipes, wires and framing before drywall covers them.
Fees: Fixr $150–$900 nationally; Dublin $880 flat for a remodel without structural changes; Maplewood about $858 and NYC $195–$235 on a $30,000 job. See the kitchen remodel cost calculator for the project itself.
Bathroom remodel
Retiling, a new vanity and resetting the toilet in the same spot are exempt: tiling and cabinets are finish work, and R105.2 exempts removing and reinstalling a toilet as long as no pipes, valves or fixtures are replaced or moved. Moving a drain, adding a shower where there was none, or wiring a new fan, heated floor or circuit makes it permitted work. Clark County requires a plumbing permit to install any plumbing fixture, while NYC exempts plumbing fixture replacement.
Fees: Fixr $150–$1,000; Dublin $600 per bathroom remodel, $219 for a shower or tub replacement only and $168 for a ventilation fan; Maplewood about $488 and NYC $156–$196 on a $15,000 remodel. See the bathroom renovation calculator.
Basement finishing
Finishing a basement creates habitable space, and Clark County lists converting a basement to living space as permitted work. Anne Arundel County, Maryland's handout summarizes the IRC 2021 rules the inspector checks:
| Item | Requirement |
|---|---|
| Habitable room | at least 70 sq ft, no side under 7 ft |
| Ceiling height | 7 ft 0 in habitable rooms; 6 ft 8 in other areas; 6 ft 4 in under beams and ducts |
| Emergency escape opening | one per basement and per sleeping room; 5.7 sq ft net clear, 24 in high, 20 in wide, sill at most 44 in |
| Smoke alarms | hard-wired with battery backup |
The same handout says electrical, mechanical and plumbing work is subject to field inspection, and that homes with an existing sprinkler system need a separate sprinkler permit unless a licensed sprinkler contractor confirms compliance.
Fees: Fixr $200–$1,500. Maplewood charges $120 for the electrical permit on a basement finish (up to 10 circuits and two inspections), on top of the building permit. Price the project with the basement finishing calculator.
Decks
The IRC exempts a deck only if it meets all four tests: 200 sq ft or less, no more than 30 inches above grade at any point, not attached to the house, and not serving the required exit door. Clark County applies the same test. Everything else needs a permit, because an attached or raised deck depends on footings and a ledger connection that can't be checked once the boards are down.
Fees: Fixr $100–$500; Maplewood $145 plus a $75 plan review fee. See the deck building calculator.
Roof replacement
Clark County requires a re-roofing permit for all buildings, while NYC exempts non-structural roof repair. Where a re-roof permit is required, the inspection is the chance to check the roof deck and flashing while they are exposed.
Fees: Fixr $100–$500 nationally; Maplewood $145, Sammamish $269 and Dublin $326. See the roof replacement calculator.
Windows, doors and siding
Rules split here more than anywhere. Fixr notes that some municipalities require a permit for any window replacement while most require one for structural changes. Clark County requires a permit to replace any window or siding. Cutting a new opening or enlarging one is a structural change, the case Fixr says most towns permit. A basement or bedroom window also has to meet the emergency escape size in the basement table above.
Fees: Fixr $50–$300 for windows; Maplewood $145 each for window replacement, siding or an egress window; Dublin $367 for the first five windows and $13 for each one after. See the window replacement calculator and the egress window calculator.
Electrical
The electrical exemptions in the table above are narrow. New circuits, a panel replacement, a service upgrade or an EV charger circuit need an electrical permit.
Fees: This Old House puts electrical permits at $75 for simple work to $900 for major rewiring on older homes. Maplewood charges $125 for a panel replacement and caps a 200-amp-or-less residential electrical permit at $225. Dublin charges $219 for the first panel, $241 for the first circuit plus $23 for each additional one, and $316 for an EV charger. See the electrical rewiring calculator.
Plumbing and water heaters
Only leak repairs, clearing stoppages and resetting a toilet are exempt under R105.2. A water heater is not on the exempt list, so a replacement normally needs a permit, and moved or new drain and supply lines always do.
Fees: Plumbing Price Guide puts a whole-house repipe permit at $100–$400. Maplewood charges $45 including one fixture opening plus $10 for each additional opening; Dublin charges $217 per plumbing fixture and $157 for a gas water heater; Sammamish charges $134 for a water heater. See the repiping calculator.
HVAC
The mechanical exemptions cover only portable equipment and minor parts, so replacing a furnace, air conditioner or heat pump needs a mechanical permit. Gas appliances may need a gas piping permit too.
Fees: Today's Homeowner puts HVAC permits at $250–$750. Dublin charges $262 per heating or AC unit; Maplewood $120 for a furnace and $40 for an AC unit; Sammamish $134 for a furnace or heat pump. See the HVAC replacement calculator.
Additions and garage conversions
Clark County lists additions, alterations and remodels, and converting a basement, attic or garage to living space, as work that needs a permit.
Fees: Bob Vila puts home addition permits at $400–$1,850 and Fixr puts garage conversion permits at $300–$1,500. On valuation tables a $100,000 addition comes to about $1,942 in Maplewood and about $2,109 in Sammamish before its technology fee. See the home addition calculator and the garage conversion calculator.
New York City: What a Renovation Permit Costs
New York sets its fees in the Administrative Code, Table 28-112.2. Local Law 56 of 2016 cut the rate for one-, two- and three-family houses, and the Department of Buildings applied it from January 17, 2017.
| NYC alteration, one- to three-family house | Fee |
|---|---|
| Minimum filing fee, covers the first $5,000 of work | $130 or $170, depending on the alteration type |
| Each additional $1,000 of work | $2.60 |
| $15,000 bathroom | $156–$196 |
| $30,000 kitchen | $195–$235 |
| $100,000 renovation | $377–$417 |
The schedule allows the Department to raise these rates by rule, so confirm the current fee when you file. Work without a permit is far more expensive: after a December 2017 law, the DOB's penalty on a one- or two-family home is six times the permit fee, with a $600 minimum and a $10,000 maximum.
Retroactive Permits: What Legalizing Unpermitted Work Costs
Fixr notes that a retroactive (after-the-fact) permit is still possible: the inspector checks the wiring, plumbing and framing, and the town may ask for blueprints and a current survey. The fee is the normal permit plus a penalty:
- Maplewood, MN: an investigation fee of up to the permit fee ("double permit fee or $100 per hour").
- Sammamish, WA: a fee equal to the permit fee for work performed without a permit.
- New York City: six times the permit fee, $600 minimum, $10,000 maximum, for one- and two-family homes.
- Nationally: Fixr says penalties range from double permit fees to a fine per day or a lien on the home.
For a $30,000 kitchen done without a permit:
| Place | With a permit | After the fact |
|---|---|---|
| Maplewood, MN | about $858 | up to about $1,378 |
| Sammamish, WA | about $1,266 + tech fee | about $2,033 + tech fee |
| New York City | $195 | about $1,365 |
Those totals leave out the larger cost: opening finished walls and ceilings so the inspector can see the work, then closing them again. Unpermitted work from a previous owner leaves three options: a retroactive permit with any fixes the inspector requires, disclosure as-is at sale, or removal. Fixr notes that banks and insurers may refuse a mortgage or coverage without the paperwork, which is why the first option is usually worth it when the work is sound.
What the Permit Fee Pays For
The fee buys a plan review before work starts, inspections at set stages (typically a rough-in before walls close and a final at the end), and a permanent record in the property file that buyers, lenders and insurers rely on. Schedule inspections early; a late rough-in inspection is a common reason a job stalls.
How to Find Your Exact Fee
- Find your fee schedule. Search "your city or county building permit fee schedule". Look for a flat fee for your job type, then the valuation table, plan review percentage and surcharges.
- Call the permit counter. Ask which permits the scope needs (building, electrical, plumbing, mechanical) and how each is priced. It costs nothing.
- Ask who pulls the permit. A licensed contractor usually pulls it under their license; if you pull it as the owner, you take on responsibility for the work meeting code.
- Get permit fees into every bid. Ask whether permit, plan review and trade permit fees are included, and ask for the receipt. A bid that leaves them out is not cheaper, only incomplete.
- Budget before you compare quotes. Add permits to the budget up front, alongside a contingency reserve for problems found once walls open.
Sources
How we use these sources: methodology.
- City of Federal Way, Residential Permit Exemptions — the IRC section R105.2 list of work exempt from permit, by trade (page © 2024, fetched October 30, 2026). link
- Jaspector, Permits Are Required Before Residential Work Unless the Code or AHJ Exempts It — IRC 2021 R105.1 (when a permit is required) and R105.2.2 (ordinary repairs exclude cutting structural members and changing egress), paraphrased from the ICC model code (fetched October 30, 2026). link
- Clark County Community Development (Washington), Residential permits — permits for additions, remodels, basement and garage conversions, re-roofing, windows and siding, plumbing fixtures; deck, fence and shed exemptions; state electrical permits (fetched October 30, 2026). link
- NYC Department of Buildings, Do I Need a Permit? — work that doesn't need a DOB permit (fetched October 30, 2026). link
- Anne Arundel County Department of Inspections and Permits, Finished Basement — IRC 2021 room size, ceiling height, escape opening, smoke alarm, sprinkler and field inspection rules (06-23-2024). link
- City of Dublin, California, FY2026-27 Updated Fee Schedule: Residential Permits — every Dublin flat fee quoted here (fees effective July 1, 2026). link
- City of Maplewood, Minnesota, 2026 Fee Schedule — valuation table, plan review, flat, trade and investigation fees quoted here (2026). link
- City of Sammamish, Washington, 2026 Fee Schedule: Development Review, Permits, and Related Fees — valuation table, plan review, technology, re-roof, energy code, mechanical and work-without-permit fees quoted here (2026). link
- New York City Council, Local Law 56 of 2016 — Administrative Code Table 28-112.2 filing fees for alterations to one-, two- and three-family dwellings (approved May 10, 2016). link
- NYC Department of Buildings, Permit Fees for One-, Two-, or Three-Family New Buildings and Alteration Applications — $2.60 per $1,000 rate in effect from January 17, 2017 (service update, January 2017). link
- NYC Department of Buildings, Civil Penalties Increased for Work Without a Permit — six times the permit fee, $600 minimum, $10,000 maximum on one- and two-family dwellings (service notice, January 2018). link
- Fixr, Building Permit Cost — kitchen, bathroom, basement and garage conversion permit ranges; $0.15–$0.85 per sq ft; retroactive permits and penalties (updated August 29, 2025). link
- Fixr, How Much Does a Roof Replacement Cost in 2026? — roof permits $100–$500 (updated February 4, 2026). link
- Fixr, Cost to Build Deck — deck permits from $100–$500 (updated January 11, 2023). link
- Fixr, How Much Does Window Replacement Cost in 2026? — window permits $50–$300 and when they are required (updated January 21, 2026). link
- This Old House, How Much Does an Electrician Cost? — electrical permits $75–$900 (updated June 5, 2026). link
- Today's Homeowner, HVAC Installation Cost: Real Prices & Sample Estimate — HVAC permits $250–$750 (updated September 3, 2025). link
- Plumbing Price Guide, Repiping Cost (2026 Pricing Guide) — whole-house repipe permits $100–$400 (updated March 2026). link
- Bob Vila, Building a Home Addition: Costs and Key Considerations, Explained — addition permits $400–$1,850 (updated May 21, 2024). link
- This Old House, How Much Does Home Renovation Cost? (2026 Pricing) — permits for a whole-house renovation $500–$2,500, citing Angi (updated March 31, 2026). link
Related
- How renovation contingency budgets work — the reserve for problems found once walls open
- How to hire a renovation contractor — licensing, bids and who pulls the permit
- How to plan a home renovation — where permits fit in the schedule
- Permit pull — what pulling a permit means
- Whole house remodel cost calculator
Frequently Asked Questions
How much does a kitchen remodel permit cost?
Fixr puts a kitchen remodel permit at $150–$900 nationally. Local schedules show the spread: Dublin, California charges a flat $880 for a kitchen remodel without structural changes (fees effective July 1, 2026), Maplewood, Minnesota's 2026 valuation table plus 65% plan review comes to about $858 on a $30,000 job, and New York City's alteration filing fee on the same job is $195–$235. Moving plumbing, adding circuits or removing a wall can add trade permits.
How much does a bathroom remodel permit cost?
Fixr's national range for a bathroom permit is $150–$1,000. Dublin, California charges $600 per bathroom remodel and $219 for a shower or tub replacement only (fees effective July 1, 2026). On a $15,000 remodel, Maplewood, Minnesota's 2026 valuation table plus plan review comes to about $488, and New York City's filing fee is $156–$196. Retiling or swapping a vanity is finish work the IRC exempts from permits.
Which renovations don't need a permit?
IRC section R105.2, as published by Federal Way, Washington, exempts painting, papering, tiling, carpeting, cabinets, countertops and similar finish work; one-story detached sheds up to 200 sq ft; and decks up to 200 sq ft that sit no more than 30 inches above grade, aren't attached to the house and don't serve the required exit door. Stopping leaks, clearing clogs and resetting a toilet without moving pipes are exempt too. Towns amend the list, so check yours.
How much does a retroactive permit cost?
Usually the normal permit fee plus an investigation fee or penalty. Maplewood, Minnesota charges an investigation fee of up to the permit fee; Sammamish, Washington adds a fee equal to the permit fee. New York City charges six times the permit fee on one- and two-family homes, at least $600 and at most $10,000. On a $30,000 kitchen that is about $1,365 in NYC instead of $195, before the cost of opening walls for inspection.
How much does a renovation permit cost in NYC?
For a one-, two- or three-family house, the Department of Buildings' alteration filing fee is a $130 or $170 minimum covering the first $5,000 of work, plus $2.60 for each additional $1,000 (Administrative Code Table 28-112.2, as amended by Local Law 56 of 2016). A $30,000 renovation comes to $195–$235 and a $100,000 one to $377–$417. On one- and two-family homes, work done without a permit draws a penalty of six times the fee.
Do I need a permit to replace a roof or windows?
Often, yes. Clark County, Washington requires a re-roofing permit for all buildings and a permit to replace any window or siding. Fixr says some towns require permits for all window replacements and most do for structural changes. In 2026 schedules a re-roof costs $145 in Maplewood, Minnesota, $269 in Sammamish, Washington and $326 in Dublin, California; Fixr's national ranges are $100–$500 for a roof and $50–$300 for windows.
Do I need a permit to finish a basement?
Almost always, because you are creating living space. Clark County, Washington lists converting a basement to living space as permitted work. Anne Arundel County, Maryland's IRC 2021 handout requires a 5.7 sq ft emergency escape opening, 7-foot ceilings in habitable rooms and hard-wired smoke alarms, and puts electrical, mechanical and plumbing work under field inspection. Fixr puts basement permits at $200–$1,500.
Does a deck need a permit?
Most do. The IRC exempts only decks of 200 sq ft or less that are no more than 30 inches above grade at any point, are not attached to the house and do not serve the required exit door; Clark County, Washington applies the same test. Attached or raised decks need their footings and ledger inspected. Fixr puts a deck permit at $100–$500, and Maplewood, Minnesota charges $145 plus a $75 plan review fee in 2026.
Are permit fees included in contractor quotes?
Not always, so ask by name: building permit, plan review and each trade permit. The amounts matter when you compare bids. This Old House, citing Angi, puts permits for a whole-house renovation at $500–$2,500, and Maplewood, Minnesota's 2026 schedule adds plan review at 65% of the building permit fee. A bid that leaves these out is not cheaper, only incomplete. Ask for the permit receipt so you see the fee actually paid.